The project success is strongly connected to its logistics. About a year of planning preceeded the operation. Method statements were established to overland / internal haulage, erection and electromechanical assembling procedures, and to enable the reception of the overweight / dimension pieces through the offshore port of Barra dos Coqueiros. This port is linked to shore by a 2,6km long narrow bridge.